Qatargas achieves major milestone with North Field Bravo Living Quarters Expansion project
Qatargas has achieved a major milestone with its North Field Bravo (NFB) Living Quarters Expansion (LQX) Project as it safely and successfully completed the onshore fabrication of the living quarters’ structure locally, a first in the country.
The fabrication was done by Nakilat-Keppel Offshore Marine (N-KOM) at the Erhama Bin Jaber Al Jalahma Shipyard. The project is significant for Qatar as it is for the first time that a major offshore living quarter’s structure has been entirely fabricated at a local yard in the country.
Qatargas organised a ceremony to mark the sail-away of the jacket and topside of the structure at Ras Laffan. The event was attended by Qatargas’ shareholders and senior executives, N-KOM, and the project’s contractor, Rosetti Marino.
“This project is a historic milestone for Qatar as it highlights a new and important capability. This achievement showcases the capabilities, skills and resources which are available locally at the Erhama Bin Jaber Al Jalahma Shipyard for the fabrication of large and complex offshore structures,” said Khalid bin Khalifa al-Thani, chief executive, Qatargas.
Qatargas had awarded the engineering procurement and construction contract for the LQX project to Rosetti Marino that undertook engineering designs in Italy. All the fabrication work was undertaken by N-KOM at the Erhama Bin Jaber Al Jalahma Shipyard at Ras Laffan Port.
The project provides for additional living quarters which will increase the capacity of the NFB Offshore living quarters by 90 personnel on board. When fully installed, this will allow for the catering of additional operational requirements.
The project work scope includes the construction of a four-legged jacket and piles weighing about 2,200 tonnes. This will support the new living accommodation platform weighing around 2,800 tonnes and consisting of five decks, a fully equipped helideck, six bridge links to existing living quarters, services and utilities.
The project has recently achieved 2.5mn safe man-hours without any lost time incidents with a peak manpower rate of over 900 people. The next major milestone of the project is the safe transportation and installation of the 5,000 tonnes of structure to offshore NFB this month. The load out, sail away and installation activities will be carried out by subcontractor Heerema using their heavy lift vessel ‘Aegir’.
“This project is not only a milestone achievement for Qatar but also an excellent testament to N-KOM’s experience in handling offshore fabrication projects,” according to Nakilat chief executive Abdullah Fadhalah al-Sulaiti.
The original NFB accommodation, installed in 1995, was designed for the operational needs of Qatargas Trains 1 and 2. The offshore accommodation expansion project was initiated to cater to the changes in the operational requirements following various expansion projects. Brownfield modifications will also be done on the existing living quarters and platform to properly integrate the new additional living quarters.