The Marjan oil and gas collection and transportation platform is seen as breakthrough of construction technology of large-scale offshore oil and gas platform for the Chinese builders, weighing more than 17,200 tons, making it one of the world’s largest.
The platform is expected to collect and transport 24 million tonnes of crude oil and 7.4 billion cubic meters of associated gas every year. Its platform scale, pipeline types and sizes, and system complexity all setting new records compared to similar platforms.
Construction of the project took 34 months.
Delivery of the platform project will help the Chinese industry players transform from sub-contractor to main-contractor in global offshore engineering market, said China Offshore Oil Engineering.
The platform will be transported to its installation site 6,400 nautical miles away in the waters off Saudi Arabia at the end of August to improve Marjan oilfield’s production capacity.